NEW QUESTION 58
Which is a type of issue?
- A. A lesson
- B. A risk with an estimated high impact
- C. A request for change
- D. An Exception Report
Answer: C
NEW QUESTION 59
Which is a purpose of a Project Brief?
- A. Enable the assembly of the project mandate
- B. Describe how changes to products will be controlled
- C. Provide a solid basis for the initiation of the project
- D. Describe the reporting requirements of the various layers of management involved with the project
Answer: C
NEW QUESTION 60
Which product records any project outcomes perceived as negative by stakeholders?
- A. Project Product Description
- B. Business Case
- C. Project Plan
- D. CommunicationManagement Strategy
Answer: B
NEW QUESTION 61
Which statement applies to Stage Plans?
- A. Always have the same duration as the Project Plan
- B. Assist the Project Manager in the day-to-day running and control of the project
- C. Are produced at the same time as the Project Initiation Documentation
- D. Provide a baseline against which the Project Board monitor overall progress
Answer: B
NEW QUESTION 62
To meet the minimum requirements for applying the progress theme, what must be considered?
- A. Who is responsible for reporting on progress
- B. How time-driven reports will be produced
- C. Which management products will be baselined
- D. How lessons will be learned
Answer: B
Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes
NEW QUESTION 63
What should the benefits management approach define?
- A. The suitability of the project management team structure
- B. What will be used to record the effectiveness of the project's approaches
- C. What actions will be taken to ensure the project's outcomes are achieved
- D. How the project has progressed against its plans
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 64
Which is a recommended quality review team role?
- A. Project Manager
- B. Assurance
- C. Project Support
- D. Administrator
Answer: D
NEW QUESTION 65
Which is an objective of the 'directing a project' process?
- A. To provide an interface between the project and corporate management
- B. To ensure the stage products are delivered to the stated quality standards
- C. To respond to the project mandate by starting up a project
- D. To tailor the project's products and roles so that the project suits the circumstances
Answer: A
Explanation:
Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ
NEW QUESTION 66
Which is a minimum requirement for applying the plans theme?
- A. The team managers in the project must prepare team plans
- B. Scope tolerance must be prioritized using MoSCoW
- C. The project must have at least two management stages
- D. The project plan must be presented as a Gantt chart
Answer: A
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Plans_Theme
NEW QUESTION 67
Where should a team manager look for information about the quality required for a product?
- A. Quality management approach
- B. Product description
- C. Project initiation documentation
- D. Team plan
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2
NEW QUESTION 68
Which should be funded from a change budget?
- A. A fallback plan
- B. The Starting up a Project process
- C. A change to a plan, within allocated tolerances, due to poor estimating
- D. An agreed change to the scope of a project
Answer: D
NEW QUESTION 69
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?
- A. Directing, managing and delivering levels
- B. Project board, project manager and project assurance roles
- C. Business, user and supplier interests
- D. Corporate, programme management or the customer parties
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Define_roles_and_responsibilities
NEW QUESTION 70
Which role is part of the project management team?
- A. Quality assurance
- B. Change Authority
- C. Stakeholder
- D. Corporate or programme management
Answer: B
NEW QUESTION 71
Which is an objective of the 'starting up a project' process?
- A. To select the project mandate
- B. To approve the initiation stage
- C. To appoint the project management team
- D. To define the project quality management approach
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Starting_Up_a_Project#Purpose
NEW QUESTION 72
Which statement about the quality review technique is FALSE?
- A. It supports the management of future changes by providing a baseline for a product
- B. It defines the quality responsibilities of the project team
- C. It is used to gain wider acceptance of a product by involving key interested parties
- D. It enables a check to be made on a product's fitness for purpose
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 73
Which is performed as part of the recommended risk management procedure?
- A. Resolution of conflicts between the project and the programme board
- B. Review of risk management practices to ensure that they are performed effectively
- C. Sending of information about risks tothe project to project stakeholders
- D. Allocation of a budget to investigate issues facing the project
Answer: C
NEW QUESTION 74
Which is a task of product-based planning?
- A. Identify activities and dependencies
- B. Produce Product Status Accounts
- C. Prepare the Work Packages
- D. Write the Project Product Description
Answer: D
NEW QUESTION 75
In which process is the work to be done assigned to a team manager?
- A. Managing product delivery
- B. Managing a stage boundary
- C. Controlling a stage
- D. Directing a project
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage
NEW QUESTION 76
Who carries out audits that are independent of the project?
- A. Project Manager
- B. Project Assurance
- C. Project Support
- D. Quality assurance
Answer: D
NEW QUESTION 77
Which should be funded by a change budget?
- A. Increase in agreed scope
- B. Handover activities
- C. Change Authority
- D. Initiation stage
Answer: A
NEW QUESTION 78
Which is an objective of the 'directing a project' process?
- A. To define how risks, issues and changes will be managed
- B. To ensure corporate or programme management has an interface to the project
- C. To obtain approval for completed products
- D. To review and approve a project mandate
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Directing_a_Project#Objective
NEW QUESTION 79
Which is a purpose of the 'closing a project' process?
- A. To establish mechanisms for forecasting project objectives
- B. To provide the project board with information to judge the success of a stage
- C. To confirm the project has nothing more to deliver
- D. To establish mechanisms to judge whether the project is still viable
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Closing_a_Project#Objective
NEW QUESTION 80
What is an advantage of dividing the project into stages?
- A. The project can be authorized by the project manager on a stage by stage basis
- B. the project board can delegate management of the project to team managers
- C. Detailed plans can be prepared closer to the time events will take place
- D. The project brief can be updated towards the end of each stage
Answer: C
Explanation:
Section: Volume B
Explanation
NEW QUESTION 81
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
- A. the project board
- B. the project manager
- C. corporate, programme management or the customer
- D. the change authority
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 82
Which theme estimates the cost of delivering the project?
- A. Plans
- B. Change
- C. Business case
- D. PROGEESS
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case
NEW QUESTION 83
......
How to book the PR2F Exam
These are following steps for registering the Exin PR2F exam. Step 1: Visit to Pearson VUE Exam Registration Step 2: Signup/Login to Pearson VUE account Step 3: Search for Exin PR2F Exam Certifications Exam Step 4: Select Date, time and confirm with payment method
Free Sales Ending Soon - 100% Valid PRINCE2-Foundation Exam: https://prep4sure.examtorrent.com/PRINCE2-Foundation-exam-papers.html