NEW QUESTION 58
Which is a type of issue?

  • A. A lesson
  • B. A risk with an estimated high impact
  • C. A request for change
  • D. An Exception Report

Answer: C

 

NEW QUESTION 59
Which is a purpose of a Project Brief?

  • A. Enable the assembly of the project mandate
  • B. Describe how changes to products will be controlled
  • C. Provide a solid basis for the initiation of the project
  • D. Describe the reporting requirements of the various layers of management involved with the project

Answer: C

 

NEW QUESTION 60
Which product records any project outcomes perceived as negative by stakeholders?

  • A. Project Product Description
  • B. Business Case
  • C. Project Plan
  • D. CommunicationManagement Strategy

Answer: B

 

NEW QUESTION 61
Which statement applies to Stage Plans?

  • A. Always have the same duration as the Project Plan
  • B. Assist the Project Manager in the day-to-day running and control of the project
  • C. Are produced at the same time as the Project Initiation Documentation
  • D. Provide a baseline against which the Project Board monitor overall progress

Answer: B

 

NEW QUESTION 62
To meet the minimum requirements for applying the progress theme, what must be considered?

  • A. Who is responsible for reporting on progress
  • B. How time-driven reports will be produced
  • C. Which management products will be baselined
  • D. How lessons will be learned

Answer: B

Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes

 

NEW QUESTION 63
What should the benefits management approach define?

  • A. The suitability of the project management team structure
  • B. What will be used to record the effectiveness of the project's approaches
  • C. What actions will be taken to ensure the project's outcomes are achieved
  • D. How the project has progressed against its plans

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 64
Which is a recommended quality review team role?

  • A. Project Manager
  • B. Assurance
  • C. Project Support
  • D. Administrator

Answer: D

 

NEW QUESTION 65
Which is an objective of the 'directing a project' process?

  • A. To provide an interface between the project and corporate management
  • B. To ensure the stage products are delivered to the stated quality standards
  • C. To respond to the project mandate by starting up a project
  • D. To tailor the project's products and roles so that the project suits the circumstances

Answer: A

Explanation:
Reference:
https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project-process-in-princ

 

NEW QUESTION 66
Which is a minimum requirement for applying the plans theme?

  • A. The team managers in the project must prepare team plans
  • B. Scope tolerance must be prioritized using MoSCoW
  • C. The project must have at least two management stages
  • D. The project plan must be presented as a Gantt chart

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Plans_Theme

 

NEW QUESTION 67
Where should a team manager look for information about the quality required for a product?

  • A. Quality management approach
  • B. Product description
  • C. Project initiation documentation
  • D. Team plan

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2

 

NEW QUESTION 68
Which should be funded from a change budget?

  • A. A fallback plan
  • B. The Starting up a Project process
  • C. A change to a plan, within allocated tolerances, due to poor estimating
  • D. An agreed change to the scope of a project

Answer: D

 

NEW QUESTION 69
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

  • A. Directing, managing and delivering levels
  • B. Project board, project manager and project assurance roles
  • C. Business, user and supplier interests
  • D. Corporate, programme management or the customer parties

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Define_roles_and_responsibilities

 

NEW QUESTION 70
Which role is part of the project management team?

  • A. Quality assurance
  • B. Change Authority
  • C. Stakeholder
  • D. Corporate or programme management

Answer: B

 

NEW QUESTION 71
Which is an objective of the 'starting up a project' process?

  • A. To select the project mandate
  • B. To approve the initiation stage
  • C. To appoint the project management team
  • D. To define the project quality management approach

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Starting_Up_a_Project#Purpose

 

NEW QUESTION 72
Which statement about the quality review technique is FALSE?

  • A. It supports the management of future changes by providing a baseline for a product
  • B. It defines the quality responsibilities of the project team
  • C. It is used to gain wider acceptance of a product by involving key interested parties
  • D. It enables a check to be made on a product's fitness for purpose

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 73
Which is performed as part of the recommended risk management procedure?

  • A. Resolution of conflicts between the project and the programme board
  • B. Review of risk management practices to ensure that they are performed effectively
  • C. Sending of information about risks tothe project to project stakeholders
  • D. Allocation of a budget to investigate issues facing the project

Answer: C

 

NEW QUESTION 74
Which is a task of product-based planning?

  • A. Identify activities and dependencies
  • B. Produce Product Status Accounts
  • C. Prepare the Work Packages
  • D. Write the Project Product Description

Answer: D

 

NEW QUESTION 75
In which process is the work to be done assigned to a team manager?

  • A. Managing product delivery
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Directing a project

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage

 

NEW QUESTION 76
Who carries out audits that are independent of the project?

  • A. Project Manager
  • B. Project Assurance
  • C. Project Support
  • D. Quality assurance

Answer: D

 

NEW QUESTION 77
Which should be funded by a change budget?

  • A. Increase in agreed scope
  • B. Handover activities
  • C. Change Authority
  • D. Initiation stage

Answer: A

 

NEW QUESTION 78
Which is an objective of the 'directing a project' process?

  • A. To define how risks, issues and changes will be managed
  • B. To ensure corporate or programme management has an interface to the project
  • C. To obtain approval for completed products
  • D. To review and approve a project mandate

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Directing_a_Project#Objective

 

NEW QUESTION 79
Which is a purpose of the 'closing a project' process?

  • A. To establish mechanisms for forecasting project objectives
  • B. To provide the project board with information to judge the success of a stage
  • C. To confirm the project has nothing more to deliver
  • D. To establish mechanisms to judge whether the project is still viable

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Closing_a_Project#Objective

 

NEW QUESTION 80
What is an advantage of dividing the project into stages?

  • A. The project can be authorized by the project manager on a stage by stage basis
  • B. the project board can delegate management of the project to team managers
  • C. Detailed plans can be prepared closer to the time events will take place
  • D. The project brief can be updated towards the end of each stage

Answer: C

Explanation:
Section: Volume B
Explanation

 

NEW QUESTION 81
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

  • A. the project board
  • B. the project manager
  • C. corporate, programme management or the customer
  • D. the change authority

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 82
Which theme estimates the cost of delivering the project?

  • A. Plans
  • B. Change
  • C. Business case
  • D. PROGEESS

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case

 

NEW QUESTION 83
......


How to book the PR2F Exam

These are following steps for registering the Exin PR2F exam. Step 1: Visit to Pearson VUE Exam Registration Step 2: Signup/Login to Pearson VUE account Step 3: Search for Exin PR2F Exam Certifications Exam Step 4: Select Date, time and confirm with payment method

 

Free Sales Ending Soon - 100% Valid PRINCE2-Foundation Exam: https://prep4sure.examtorrent.com/PRINCE2-Foundation-exam-papers.html