Accurate & Verified 2022 New C_ACTIVATE13 Answers As Experienced in the Actual Test!


How to get prepared for the SAP C_ACTIVATE13 Certification Exam?

To get prepared for the SAP C_ACTIVATE13 Certification Exam you just need to follow a few steps. You need to have a plan to get prepared for the SAP C_ACTIVATE13 Certification Exam. The prep process includes these steps. Firstly, get the preparation source. There are not many sources available in the market, to get ready for the C_ACTIVATE13 exam. You can get the preparation source from the official website of the SAP. Desktop and online preparation are available on the official website of the SAP. Explore phase is very important for the preparation. You need to check the concepts and processes involved in the SAP C_ACTIVATE13 Certification Exam.

Secondly, prepare for the SAP C_ACTIVATE13 Certification Exam by reading the preparation source. Thirdly, practice for the SAP C_ACTIVATE13 Certification Exam. Practice a lot and practice a lot. The SAP C_ACTIVATE13 Certification Exam contains a number of questions. It is very difficult to predict the questions of the C_ACTIVATE13 exam. C_ACTIVATE13 Dumps provides you with the most updated sample questions. You can use them to get prepared for the SAP C_ACTIVATE13 Exam. Highly rated questions are present in the SAP C_ACTIVATE13 Certification Exam. You need to practice the questions to prepare for the exam. You need to be prepared for the unexpected questions, that will be asked in the C_ACTIVATE13 exam.


How much does the SAP C_ACTIVATE13 Certification Exam cost?

The candidate must pay a non-refundable exam fee of 592 USD, for the SAP C_ACTIVATE13 Certification Exam.


The resources that you can use to get prepared for the SAP C_ACTIVATE13 Certification Exam

There are many resources to get ready for the C_ACTIVATE13 Certification Exam. A few of them are given here. You can use the books, online training, notes, and mock exams to get prepared for the exam. You can also use the official study guide, the standard workshop, and study materials. The official study guide and the study materials are available on the official website of the SAP. You can also get the preparation source from the official website of the SAP. Moreover, the candidates can also use YouTube videos to learn about the different topics of the exam. You can also get help from the online free and paid courses to get prepared for the C_ACTIVATE13 Certification Exam. You can assess and download PDF files of the sample tests of the C_ACTIVATE13 Exam, from multiple websites. You can use this pack of dump material, as many times you want. Dumpslink that is recommended by the team of experts is the bundle of practice exams and C_ACTIVATE13 Dumps of the ExamTorrent. Here you can access practice questions of the C_ACTIVATE13, according to every topic and domain with their correct answers.

 

NEW QUESTION 37
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:

  • A. Relative estimate in ideal person days that reflects the best estimate provided by the project team
  • B. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
  • C. Product Owner's relative estimate of the effort that will be needed to implement the user story
  • D. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity

Answer: A

 

NEW QUESTION 38
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:

  • A. Custom code adjustment
  • B. Sandbox system migration
  • C. Development system migration
  • D. Delta configuration
  • E. Operations impact analysis

Answer: A,C,D

 

NEW QUESTION 39
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

  • A. Fixed scope
  • B. Delta-based
  • C. On premise only
  • D. Cloud Ready
  • E. Based on Ready-to-use Content

Answer: B,D,E

 

NEW QUESTION 40
In which phase should you create a data migration strategy (LO) during a selective data transition?

  • A. Discover
  • B. Realise
  • C. Deploy
  • D. Explore

Answer: A

 

NEW QUESTION 41
Where can you find Data Migration templates?
Please choose the correct answer.
Response:

  • A. SAP Roadmap Viewer
  • B. SAP S/4HANA Migration Cockpit
  • C. SAP Best Practices Explorer
  • D. SAP Cloud Appliance Library

Answer: B

 

NEW QUESTION 42
In which SAP Activate methodology phase does the team complete the Transformation Strategy?
Please choose the correct answer.
Response:

  • A. Realize
  • B. Deploy
  • C. Explore
  • D. Prepare

Answer: D

 

NEW QUESTION 43
Which of the following tools is used to install SAP S/4HANA.
Please choose the correct answer.
Response:

  • A. Cloud Application Library
  • B. SAP Solution Manager
  • C. SWPM (Software Provisioning Manager)
  • D. Data Migration server

Answer: C

 

NEW QUESTION 44
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:

  • A. Send e-mail to SAP contact address
  • B. Join SAP S/4HANA group on SAP Community Network
  • C. Register on SAP Service Marketplace
  • D. Submit e-mail address via on-line form

Answer: D

 

NEW QUESTION 45
In which tools can the project team across the SAP Activate Methodology content including accelerators?
There are 2 correct answers to this question.
Response:

  • A. SAP Service Marketplace
  • B. Roadmap Viewer
  • C. SAP Community Network
  • D. SAP Jam

Answer: B,D

 

NEW QUESTION 46
Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question.
Response:

  • A. Data aging configuration
  • B. Value determination
  • C. Non-production systems migration
  • D. Custom code Adjustment planning

Answer: A,C

 

NEW QUESTION 47
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.

  • A. Starter system
  • B. DQAS
  • C. DEV
  • D. P-system

Answer: B,C

 

NEW QUESTION 48
In what respect is SAP Activate Methodology different from the ASAP Methodology?
Please choose the correct answer.
Response:

  • A. Supports cloud deployments
  • B. Supports only new implementations
  • C. Leverages iterative incremental build
  • D. Includes Fit/Gap analysis instead of Blueprint

Answer: D

 

NEW QUESTION 49
Which of the following content best outlines the sequence of testing within the application Design and configuration workstream in the realize phase?

  • A. User acceptance test
    String test data migration
  • B. String test
    User acceptance test
  • C. User acceptance test
    Integration test integration test
  • D. string test
    Integration test
    User acceptance test string test

Answer: D

 

NEW QUESTION 50
According to the Definition of Done, which activity must be completed for each sprint?
Please choose the correct answer.
Response:

  • A. Functionality must be tested in the Quality system (QAS)
  • B. Functionality must be released to the business
  • C. End user training must be delivered
  • D. The Solution must be built and configured in the development system (DEV)

Answer: D

 

NEW QUESTION 51
What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition?
Please choose the correct answer.
Response:

  • A. Solution validation
  • B. Readiness check
  • C. End-to-End walkthrough
  • D. Data migration

Answer: C

 

NEW QUESTION 52
What is the key characteristics of the agile project approach

  • A. Formal and detailed documentation
  • B. Frequent Quality Gates
  • C. Frequent and detailed project scheduling
  • D. Iterative build with frequent inspections

Answer: D

 

NEW QUESTION 53
In which phase do you verify that the SAP best practices content meets the customer's Business needs?

  • A. Realize
  • B. Explore
  • C. Deploy
  • D. Prepare

Answer: B

 

NEW QUESTION 54
......